Utilities | Fill Prerequisites

Fill Prerequisites show which requirements are met for meter activation and any errors that are detected.

Fill Prerequisites

Items Accessible on Fill Prerequisites Page:

Close— closes this page without continuing with the procedure.

Close

Fill Inactive— button appears until all the requirements are met.

Fill Inactive

Fill Ready— button appears when all the requirements are met.

Fill Ready

Fill Active— button appears when the meters are rotating.

Fill Active

Fill Prerequisites:

Check Mark— indicates that the requirement is met.

Check Mark

Exclamation Point— indicates that a requirement is not met or that there is an error.

Exclamation Point

View Fault— opens Diagnostics | Row Unit Controller (RUC) Row Addressing to view the active fault.

View Fault

Procedure to Modify:

Close— closes this page without continuing with the procedure.

Close

  1. Verify that seed is in the row unit hoppers, seed disks are installed, and the seed meter is prepared according to the recommendations in your implement Operator's Manual.

  2. Adjust the implement to meet all the requirements.

  1. If the Electric Power Generation (EPG) requirement is not met, select the toggle button to turn on the EPG system.

ON/OFF

NOTE: The toggle button does not appear when the requirement is met.

CAUTION: To avoid injury from rotating components:

  1. Select the Fill button. The Fill button changes from the ready state to the active state while the seed meters rotate.

Fill Ready

NOTE: The seed meters rotate for 3 seconds. Depending on the meter setup, 3 seconds might not complete the fill process. Select Fill as many times as necessary. Two fill cycles are typically adequate.

Advanced Settings— access further adjustments and less common settings.

Advanced Settings