Installing a G5 Universal or Generation 4 Universal Display

NOTE: Enable Precision Ag Applications (GreenStar or AMS) on one display only. Guidance and other applications will not function properly when multiple displays have AMS applications enabled. Select Application Configurations for more information on each configuration preset.

  1. Ensure that key switch and CommandCenter are off.

  2. Attach display harness to corner post connector and the 26-pin display connector to the back of the display.

  3. Turn key switch on.

  4. The CommandCenter searches for a second display on the implement CAN bus for approximately 60 seconds. If the CommandCenter was previously in Primary Display Mode, it displays the message “Multiple Displays Detected.”

  5. Select a configuration preset:

    Primary Display

    Multiple Display – Implement Viewer

    NOTE: If the ISOBUS implement does not have “Next VT display” function, the implement appears on the display that starts up first.

    Advanced Setup

  6. Cycle key switch off and on to save settings.

Removing a G5 Universal or Generation 4 Universal Display

  1. Ensure that key switch and CommandCenter are off.

  2. Detach display harness from the 26-pin display connector at the back of the display.

  3. Turn key switch on.

  4. The CommandCenter searches for a second display on the implement CAN bus for approximately 2—3 minutes. If the CommandCenter was previously in a Multiple Display Mode, it displays the message, “Second Display Not Found.”

  5. Cycle key switch off and on to save settings.